Fig. 30: Ball valves closed
Filling the heat interface unit
Filling the secondary circuit for
drinking water distribution
Fig. 31: Opening the fresh water ball
valve
Personnel:
n Heating and sanitary technician
Prerequisites:
n The heat interface unit has been installed and connected in
accordance with Ä Chapter 5 ‘Assembly’ on page 34.
n The water quality has been tested and found to be good.
1.
Ensure that all ball valves (Fig. 30) are closed.
2.
Check the tightness of all bolted connections and retighten if
necessary.
3.
To fill the heat interface unit, open the main supply line for
fresh water outside the heat interface unit.
4.
Slowly open the main supply line for cold water (Fig. 31/1).
ð The secondary circuit fills up.
5.
Open the hot water distribution connection (Fig. 31/2).
6.
In order to flush and bleed the lines, open the taps.
ð The drinking water system (hot) is filled, flushed and bled.
7.
ð The primary circuit fills up.
8.
Open the primary connection for the heat supply return line
(Fig. 32/1).
Filling the primary circuit
Fig. 32: Opening the ball valve for the
heating supply and heating return
V03 06/2025 Item no. 215250 EA no. 1292
Operating instructions
43
WARNING!
Risk of burns due to hot pipes!
Open the primary connection for the heat supply flow line
(Fig. 32/2).