Personnel:
Protective equipment:
Tool:
Material:
n Cloth
n The leak has been pinpointed.
n The replacement material is available ( Ä Chapter 12 ‘ Spare
parts’ on page 58).
1.
2.
3.
Loosen and remove the bolted connection at the leak using an
adjustable spanner.
4.
Collect the remaining water using a cloth.
5.
Insert the new pipe or new bolted connection.
6.
Ensure that O-ring seals are available.
7.
Tighten the new pipe or new bolted connection using an
adjustable spanner.
8.
Open the corresponding ball valve.
9.
Check the spare part for leak-tightness.
ð The leak has been repaired.
Prerequisites:
n Heating and sanitary technician
n Protective gloves
n Adjustable spanner
n Spare parts
Fig. 39: Ball valve closed
Close the ball valve (Fig. 39) of the supply line to the leaking
point so that water no longer flows through it.
If the pipes or bolted connections of the main supply lines leak,
close the main supply lines.
If the pipe section is one through which hot water flows, wait
until the pipe section has cooled down.
V03 06/2025 Item no. 215250 EA no. 1292
Operating instructions
51
Observe the flow chart (
Ä Chapter 3.1 ‘Circuits
and connection points in the heat interface
unit’ on page 23).
WARNING!
Risk of burns due to hot pipes!