Personnel:
n Heating and sanitary technician
1.
Close all the ball valves (Fig. 47).
ð The flow and return lines are closed.
2.
Switch off the electrical fuse of the heat interface unit and
secure it against being switched on again.
3.
Wait until the heat interface unit has cooled down.
ð The heat interface unit has been shut down for a short
period.
In order to remove an optional component from the
piping or install an equipment option in the piping,
the corresponding circuit must be drained
(
Ä Chapter 13.3 ‘Emptying the heat interface unit’
on page 61).
Fig. 47: Closing the ball valves
Personnel:
n Operator
1.
2.
3.
4.
5.
Close all the ball valves (Fig. 48).
ð The flow and return lines are closed.
Switch off the electrical fuse of the heat interface unit.
Drain all taps and leave them open.
Drain all of the pipes of the heat interface unit in accordance
with Ä Chapter 13.3 ‘Emptying the heat interface unit’
on page 61.
Ensure that the heat interface unit is protected against frost.
Fig. 48: Closing the ball valves
60
Operating instructions
V03 06/2025 Item no. 215250 EA no. 1292
Shutting down for a short period is appropriate if
maintenance work has to be carried out on the heat
interface unit.
Shutting down for an extended period is appropriate
if the building section will not be occupied for a
lengthy period.