Draining the primary side of the heat
interface unit
Fig. 49: Opening the valves
Draining the secondary side of the heat
interface unit
Personnel:
n Heating and sanitary technician
1.
To depressurise the primary circuit of the heat interface unit,
open the air bleed valves (Fig. 49).
2.
Shut down the central heating connection in accordance with
the project planning documents.
3.
To remove the remaining water from the pipes, loosen the
bolted connections on the adaptors and collect the remaining
water using a cloth.
ð The heating distributor has been drained.
Personnel:
n Heating and sanitary technician
1.
2.
To depressurise the secondary circuit of the heat interface unit,
open the connected taps.
To remove the remaining water from the pipes, loosen the
bolted connections on the adaptors and collect the remaining
water using a cloth.
ð The drinking water connection has been drained.
V03 06/2025 Item no. 215250 EA no. 1292
Operating instructions
61